Changes

Jump to: navigation, search

BTP300A Team 4 A2 Weekly Log

624 bytes added, 20:42, 17 November 2012
no edit summary
* 10/6 (Saturday): Assignment 2 Release 0.1 is completed
* 10/7 (Sunday): Assignment 2 Release 0.1 is submitted
 
==Week 7 ( Release 2 and 3)==
* 10/15 SVN set up for all group members
* 10/15 Programing tasks divided up for each group member
 
==Week 8 ( Release 2 and 3)==
* 10/27 initial commit of code to trunk
* individual coding
 
==Week 10 ( Release 2 and 3 coding completion)==
* 11/4 clabel ready
* 11/4 cfield ready
* 11/4 cbutton ready
* 11/6 cline ready
* 11/7 work on cdialog begins
* 11/11 cdialog completed
* 11/11 debugging of code with all classes begins
 
==Week 11 ( Release 2 and 3 overall code debugging)==
* 11/13 issue with cdialog's memory allocation
* 11/15 issue with cdialog solved
* 11/15 most other bugs solved

Navigation menu