Project Weekly Logs

627 bytes added, 10:36, 30 March 2015
4. Vasil Rimar - Norbert Curiciac
===4. Vasil Rimar - Norbert Curiciac===
 
====Week 11 (March 28)====
In this week we completed 80% of our project.
Vasil:
* Successfully completed the local database and UI development .
* Research a new memory efficient method, recommended by Google, to pull the web service data and store it on the local device.
* He used GSON, Voley and SugerORM to pull data , and store it locally on the device.
 
Norbert
* Added the markers based on the new database.
 
Work needed to be done:
1. Location List Filters (complete, pending, incomplete)
2. Map Filters (complete, pending, incomplete)
3. Login Authenticate via API
4. Prepare DETAILS page (fix drop-down models)
 
 
====Week 10 (March 21)====
Vasil: